North Texas Tollway Authority approves $35 million in Trinity Parkway contracts

Print
Email
|

by By MICHAEL A. LINDENBERGER / The Dallas Morning News

wfaa.com

Posted on August 15, 2009 at 4:45 PM

Updated Friday, Oct 16 at 4:18 PM

The North Texas Tollway Authority took some of its most decisive action yet on the Trinity Parkway project Wednesday.

The NTTA board awarded nearly $35 million in contracts for a variety of design and other services related to the controversial toll road.

Most of the money, about $30 million, will be spent to hire firms that will oversee the preliminary design of the Trinity Parkway. The road, which will be about nine miles long, will begin as a four-lane toll road through the Trinity River Corridor.

The firms will bring the proposed road to a "design threshold" of about 30 percent - an important milestone, given that the U.S. Army Corps of Engineers has said it won't evaluate the project until it sees at least that much of its design complete.

The corps must approve the road because it is being built inside a floodway.

Perhaps even more important than the design work, which is expected to be completed by the spring, is a contract for about $200,000 with Wilbur Smith Associates, a national firm specializing in projecting toll revenues and traffic.

That money will cover a preliminary traffic and revenue study, a necessary first step for NTTA to decide whether it wants to make the project one of its own toll roads or hand it off to the state once the preliminary design and other early work are completed.

NTTA has long promised to push the road forward, but it has stopped short of committing to build it, noting that the estimated price tag of $1.8 billion could easily rise, depending on when, and whether, the federal government approves its course through the levees.

Without a solid understanding of how much toll revenue the road would generate, the agency cannot determine how much it can afford to borrow to build the road.